Understand G98, G99 and G100, inverter ratings, battery capacity, application documents and category-specific connection timescales.
G99 for commercial solar and battery projects in Scotland
A grid-connection application is part of the design process, not paperwork to leave until commissioning. The correct route depends on the complete generation and storage configuration, the existing connection and the network operator's requirements.
This guide explains the questions to raise before a commercial solar installation or battery storage project. It does not replace the current engineering recommendations or the DNO's project-specific agreement.
G98, G99 and G100: different purposes
G98 generally covers fully type-tested generation with an aggregate AC rating of up to and including 16A per phase at a premises—approximately 3.68kW single-phase or 11.04kW across three balanced phases. Larger installations generally fall under G99, even where a G100 scheme limits export.
G100 concerns export limitation. An agreed export limit is not the same as the installed generation rating, and limiting export does not automatically make a larger installation eligible for G98. Check the Energy Networks Association generation-connection guidance and the SP Energy Networks G99 process.
Solar kWp, inverter kW and battery kWh
Solar panel capacity in kWp describes the DC array under standard test conditions. Inverter power in kW describes its AC output capability. Battery capacity in kWh describes stored energy, not the maximum output to the network.
Give the DNO the ratings and configuration of all generation and storage equipment, including existing equipment, shared hybrid inverters and proposed export limitation. Simply adding battery kWh does not determine the connection procedure. See SP Energy Networks electrical energy storage guidance.
Application and notification
Eligible single-premises G98 installations can be connected and then notified within 28 days of commissioning. Installations outside that route generally need a G99 application and agreement before connection. Confirm the applicable procedure before work is scheduled; different small-generation procedures and existing connection agreements can affect the requirements.
For a retrofit, include existing solar and the proposed battery inverter in the assessment. Do not treat the new battery as an isolated addition. Our Edinburgh home battery guide explains the homeowner questions separately.
What information should be ready?
New — buy online
Configure your FOX ESS battery or EV charger in minutes
Transparent pricing, from £4,070 installed at 0% VAT — reserve your system with a deposit and we'll handle the rest.
A submission commonly needs the site and supply details, equipment ratings and type-test information, a single-line diagram, protection arrangements and any proposed export-limitation design. The precise documents depend on the application category.
Check that diagrams, inverter specifications and the application describe the same design. If equipment or operating arrangements change, confirm whether the application or agreement needs updating. A complete application reduces avoidable requests for missing information, but cannot guarantee available network capacity.
How long does a connection offer take?
Published quotation standards depend on the connection category. SP Energy Networks lists 45 working days for LV connections involving LV works and 65 working days for connections involving HV or EHV works, from receipt of all relevant information. These are quotation timescales—not a measured average and not a guarantee of commissioning within that period.
Eligible small-generation procedures may be quicker. Network reinforcement, permissions, design changes and construction can add time after an offer. Confirm the applicable category and timetable with your DNO. Read SP Energy Networks quotation timescales and SSEN's published metered-connection performance standards.
Export limits and the financial model
An export limit can affect how much solar generation can be sold. Model self-consumption, export and curtailment separately rather than assuming every generated unit attracts an export payment.
Battery storage may help align generation with consumption, but its usable capacity, output limits, efficiency and operating schedule must be included. An export-control arrangement is not a substitute for the applicable connection agreement.
Project planning in Edinburgh and the Scottish Borders
Start with the site postcode, MPAN, existing supply and generating equipment, proposed system and consumption data. Identify the network operator for the actual site rather than assuming every Scottish property uses the same operator.
Our Haddington solar-and-battery project includes a single-to-three-phase supply upgrade. Our Scottish fleet charging project includes the grid connection supporting 18 × 200kW chargers. These are project-specific examples, not evidence that every site needs—or can avoid—the same upgrades.
Before accepting a quotation
- Which connection procedure applies, and who makes the submission?
- Does the assessment include existing generation and storage?
- Are connection works, fees and export controls included?
- What milestones depend on the DNO or other permissions?
- How does an export limit affect the yield and savings model?
- Who supplies commissioning records and confirms compliance?